« Previous Case Study
LINDE PLC - DOW PATH2ZERO PROJECT 2026 Project Description
For Dow‘s MRO facility in Fort Saskatchewan, Alberta, WF Group of Companies worked alongside York Construction to supply a comprehensive crane package designed to support the facility’s operational needs.
The project included:
• One 100-tonne overhead crane
• Three 60-tonne overhead cranes
• Two 30-tonne overhead cranes
• One 7.5-tonne motorized jib crane
• Runway steel for all crane systems
• Complete installation of the cranes and runway steel
From Crane supply and supporting steel to installation, WF Group brought each scope together under one team to help deliver an efficient, coordinated solution for the project.